Building our future: A progress report on our Stockbridge bond projects
4 mins read

Building our future: A progress report on our Stockbridge bond projects

From the Superintendent’s Desk

by Jeff Trapp

As we reflect on how grateful we are for the support of our community in passing our bond project one year ago, I want all of you to have the latest, most accurate information regarding the progress being made on our $15.1 million Bond Project Program. Please know our commitment remains focused on being careful stewards of these funds as we strive to deliver safe, updated, high-quality facilities and resources for our students.

As a reminder, the voter-approved bond funds are distributed across several district priorities:

Anticipated Distribution of Funds (*numbers are rounded): 

  • Facilities & Infrastructure = $7,000,000*
  • Interior Improvements = $2,400,000*
  • Buses = $1,700,000*
  • Technology = $3,600,000*
  • Bond Costs (design, legal, fees) = $400,000* 

Below is a summary and status update for each of our primary bond projects:

Facilities & Infrastructure

  • Cafeteria Plumbing (Jr./Sr. High School) 
    • SUMMARY:Subsurface plumbing repairs in the cafeteria area and replacement of a main water line in the cafeteria bulkhead.
    • LATEST UPDATE:The Board of Education approved the project bid ($76,591). Construction is slated for Winter Break 2026. To maximize savings, the district will utilize matching replacement flooring already owned in inventory.
  • Boiler Replacement (Heritage Elementary)
    • SUMMARY: Complete replacement of all three heating boilers for Heritage.
    • LATEST UPDATE: The board approved the project bid ($350,792). Full replacement and installation are scheduled for Spring 2027.
  • Athletic Facilities and Field Upgrades
    • SUMMARY: Complete replacement of the track, re-centering the football field, constructing new field event areas, and building a paved walking path to soccer, baseball, and softball fields.
    • LATEST UPDATE: Architectural drawings are undergoing review with our athletic input team to refine project scope and keep costs aligned with budget goals.
  • District Roof Replacements (Smith, Heritage, and High School)
    • SUMMARY: District-wide roof upgrades replacing both shingle and flat membrane roofing systems across all three school buildings.
    • LATEST UPDATE: The board approved the $1,001,274 roofing contract for Smith and Heritage, targeted for Spring/Summer 2027. High School roof estimates have been refined based on specific repair square footage.
  • Parking Lot Improvements
    • SUMMARY: Expanding the Smith Elementary parking lot to improve traffic flow and adding dedicated parking near the high school baseball/softball athletic fields.
    • LATEST UPDATE: Civil engineers are coordinating with the Ingham County Drain Commission on storm water management plans and setting up a traffic study for the Smith parking lot project.

Learning Space and Interior Improvements

  • Agriculture / CTE Barn (Jr./Sr. High School)
    • SUMMARY: Construction of a dedicated facility to support agricultural science, CTE programs, and district equipment storage.
    • LATEST UPDATE: Initial contractor estimates came back higher than expected. Our team, architects, and building inspectors are evaluating revised design alternatives.
  • Life Skills Lab (Jr./Sr. High School) 
    • SUMMARY: Development of a modern Life Skills classroom equipped with new cabinetry, kitchen workstations, laundry area, bathroom addition, and appliances.
    • LATEST UPDATE: Finalized architectural drawings are being submitted to the Board of Education for approval in Winter 2026, after which the project will go out for formal bidding.
  • Locker Rooms (Jr./Sr. High School)  
    • SUMMARY: Comprehensive renovation of the boys’ and girls’ locker rooms in the Auxiliary Gym, featuring updated lockers, team areas, showers, and storage spaces.
    • LATEST UPDATE: Stakeholder input groups have reviewed initial concepts, and revised layout plans have been submitted to architects to finalize cost estimates.
  • Restroom Remodel (Smith Elementary) 
    • SUMMARY: Full remodel of the 2nd-grade hallway restrooms, paired with a partial remodel (new tile and fixtures) in the 1st-grade hallway restrooms.
    • LATEST UPDATE: Currently in the final design phase, with drawings scheduled for bid for Spring 2027.
  • Cafeteria and Kitchen (Smith Elementary) 
    • SUMMARY: Renovations to the Smith cafeteria area and kitchen layout, updates in cooking equipment, new walk-in refrigerator and freezer.
    • LATEST UPDATE: Design revisions have been submitted to architects, with drawings scheduled for bid for Spring 2027.

Technology and Buses

  • Buses
    • LATEST UPDATE: The district recently purchased a gasoline-powered bus equipped with undercarriage storage for student trips, complementing our ongoing fleet updates.
  • Technology Upgrades
    • SUMMARY: Purchase 28 Newline interactive display boards for Junior/Senior High School classrooms, matching the technology already successfully utilized in our elementary schools.

Again, we remain deeply grateful for the community’s support as we invest in the resources and facilities that serve our students every day. Please feel free to reach out to me with any questions as these projects progress.

We Are Stockbridge. Go Panthers!

Jeff Trapp, Superintendent
Stockbridge Community Schools